SRU Unit Shutdown:
SRU Unit Condenser Inlet / Outlet cover removal and re-fixing as per client approved Rigging plan
Sulphur removal using not spark tools, hydro jetting the condenser tubes and testing
Sulphur pit SEAL POT removal / cleaning after inspection re-installation
TSA (Thermal Spray Aluminum) coating for sulphur pit, condenser, reactor and KV valves weld crack areas.
AQUA MILLING activity for steam jacket / Rendon lines as per client procedures.
Steam Jacket / Rendon line Hydro testing as per client methods.